As per our previous article, the President has signed into law the Carbon Tax Act No 15 of 2019, which came into effect from 1 June 2019.
Our clients that are contractors in the construction industry continue to receive price increase notification letters from suppliers (particularly in the cement and steel industries).
This is the second in our series of articles which sets out how a contractor may claim additional compensation from employers should such price increases have an effect on the contract price.
The second contract form in our series is the JBCC Principal Building Agreement (both the 2007 and 2018 versions). How do each of these contracts allow the contractor to claim additional compensation in the event of a change in the laws of South Africa? Do they … or don’t they?
Unlike the FIDIC Red Book that we looked at in series one (which has a specific clause that enables the contractor to claim compensation based on a change in the laws) the 2007 PBA has no such clause.
Instead, clauses 32.5 and 32.6 of the 2007 PBA state:
In other words, the 2007 PBA prescribes the circumstances where expense and loss can be claimed by the contractor. None of these circumstances are as a result of a “change in the law”.
On the other side of the coin, the expense and loss clause in the 2018 JBCC PBA states:
The 2018 PBA does not list the circumstances in which expense and loss can be claimed. It seems to leave it wide open. The contractor merely notifies of expense and/or loss for which provision was not required in the contract sum. The contract sum is the tendered amount – the contractor would not have been able to provide for increases in prices due to a change in the law that occurred after the date of tender submission.
In order to be in the running for a potential award of additional compensation by the principal agent, the contractor will have to ensure that it sticks to the time frames outlined in clause 26.5 – or it forfeits its claim. This time bar may be applied strictly. Contractors who receive price increase notification letters from suppliers should ensure that the supplier accurately describes the reason for the price increase, and the contractor should be able to provide a detailed and substantiated claim to the principal agent in this regard.
Summary
The 2007 PBA does not appear to have a clause that enables the contractor to claim expense and loss as a result of a change in the laws. The 2018 PBA is less prescriptive in terms of what expense and/or loss is claimed by the contractor. A condition precedent to an entitlement for expense and/or loss is compliance with the provisions of clause 26.5, and the ability to submit a detailed and substantiated claim to the principal agent, taking into account any contract price adjustment provisions.
Author: Natalie Reyneke, Senior Associate